Use this article to turn an approved technical recommendation into a scheduled, one-time corrective job. It is intended for Managers who plan follow-up work in the Scheduler.
NoteRequired role: Manager
Before You Get Started
- The recommendation must be approved. Only approved recommendations reach the planner.
- The recommendation must be raised against an asset, system, or area. Recommendations raised against a Structure or the whole Location do not add activities to the Control Schema and do not appear in the planner.
- Suggested activities left at the default one-time frequency become one-time activities. If an activity was changed to a daily, weekly, or monthly frequency, it is planned as recurring work instead.
Approve the recommendation
If the recommendation still needs approval, review it before planning the visit.
- Open Locations, then Recommendations.
- Under Filters, set Status to Needs Approval and select Apply Filters.
- Select the draft recommendation. Review its Suggested activities, Problem, Solution, Priority, and Attachments.
- Make any required changes, then select Update & review. If no changes are needed, select Update & review without editing. The recommendation status becomes Approved.
Problem and Solution are required. A recommendation without suggested activities can be approved, but it cannot close automatically because there is no work to match.
Schedule the one-time follow-up job
- Open Scheduler from the sidebar.
- Select To plan. This option is available in week, day, and agenda views, but not in the month view.
- Find the follow-up card marked One-time and select it.
- In New Visit, check the prefilled Location and Date.
- Adjust From and Until if needed. They start at the current time and one hour later because a one-time card has no suggested times.
- Set Needs review as required and confirm the Assignees.
- Select Schedule.
The visit is marked One-time. If the visit also contains recurring jobs, it is marked incl. one-time.
Understand what appears in the planner
- Approving a recommendation adds each suggested activity to the asset, system, or area's Control Schema at the frequency set on the activity.
- An all-one-time activity card has a One-time badge. A card containing both one-time and recurring work has an incl. one-time badge.
- A one-time card disappears after its job is scheduled. If the job is cancelled or skipped, the work appears again when the planner refreshes.
- If the location already has a recurring activity of the same type, the follow-up may be included in that activity's recurring card instead of appearing as a separate one-time card. Schedule the recurring card; the follow-up job is added to that visit.
- After the app reloads, unplanned work is hidden until To plan is selected again in week, day, or agenda view.
Resolve scheduling issues
- If Schedule is disabled, select an assignee. A suggested engineer is prefilled only while that engineer is active and allowed at the location.
- If no card appears, confirm that the recommendation is approved, the activity is scoped to an asset, system, or area, and To plan is enabled in a supported calendar view.
- If the activity was changed to a recurring frequency, look for its recurring planner card. It will not have a One-time badge.
What happens after the job is completed
The approved recommendation closes automatically when every suggested activity has a completed job. Partial completion does not close it. Complete the follow-up job from the visit's job list by opening its Actions tab, completing the activity form, and selecting Complete Job.
If automatic closure does not occur, the recommendation remains approved. A recommendation can also be closed manually in the web app by a user with recommendation-edit access.